LIQUID FLOW VERTICAL DOWN -ORIFICE INSTALLATION
- SHIPRA
- Topic Author
- Offline
- New Member
Less More
11 years 1 month ago - 11 years 1 month ago #8286 by SHIPRA
LIQUID FLOW VERTICAL DOWN -ORIFICE INSTALLATION was created by SHIPRA
We have a case where we need to install orifice flange for liquid (water service ) in vertical line
with liquid flow vertically downwards. Is it acceptable practice? Have any one of you have done this?
Rgds
Shipra
with liquid flow vertically downwards. Is it acceptable practice? Have any one of you have done this?
Rgds
Shipra
Please Log in or Create an account to join the conversation.
- Jop
- Offline
- Moderator
Less More
- Posts: 1053
- Thank you received: 14
11 years 1 month ago - 11 years 1 month ago #6781 by Jop
Do it once and Do it Right
Replied by Jop on topic Re: LIQUID FLOW VERTICAL DOWN -ORIFICE INSTALLATION
It has been a very long time but I remember having:
1 - Vertical Orifice run
2 - Flow up
3 - Vapor/Gas
4 - Only with review and approval of both the Process Engineer and the Instrument Engineer
1 - Vertical Orifice run
2 - Flow up
3 - Vapor/Gas
4 - Only with review and approval of both the Process Engineer and the Instrument Engineer
Do it once and Do it Right
Please Log in or Create an account to join the conversation.
- SHIPRA
- Topic Author
- Offline
- New Member
Less More
- Posts: 2
- Thank you received: 0
11 years 1 month ago - 11 years 1 month ago #6782 by SHIPRA
Replied by SHIPRA on topic Re: LIQUID FLOW VERTICAL DOWN -ORIFICE INSTALLATION
It has been a very long time but I remember having]
Thanks for feed back.
Please Log in or Create an account to join the conversation.
Moderators: Jop
Time to create page: 0.191 seconds