what are input requried to prepare piping specification sheet document?

A list of all commodities 12 years 3 months ago #4620

  • Jop
  • Jop's Avatar
  • Offline
  • Moderator
  • Posts: 1052
  • Thank you received: 14
  • Karma: 11
A list of all commodities along with the following for each:
Maximum operating pressure
Maximum operating temperature
Any known short time upset condition
The corrosiveness of the commodity
The planned life of the plant
The corrosion allowance


p.s.: There are times when you really should spell out the words of your question (example: pms vs. Piping Material Specifications).