Dear All,
I am aware about the procedure of keeping Piping Master P&ID set while doing detail design but managing the inputs on this P&IDS is crucial....!
Keeping in mind the whole life cycle of detail engineering design, I would like to know.....
-What is the ideal procedure to have Master P&ID?
-How we can make everybody aware & let them know the importance of the Master P&ID?
-Are we going to use some colour coding like RED for addition, Blue for deletion & others?
-How frequently we should communicate these piping mark ups to process department for approval & implementation on the latest P&IDs?
-How we can have a real control over this activity?
-Do we need a special person appointed on the project for this particular activity or there is no need of this?
-Most commonly, we will have these kind of mark ups for example: Combining utility lines, PSV outlet lines, addition or deletion of reducers....what are the mark ups other than these are most common? Please give examples?
-Can we make a 'SET procedure' for this activity & circulate it amongst the piping team? What can be the procedure?
It would be great if the most senior & active pipers like Jop, Anton would advice on the above activity...it will be a great HELP for everybody..!
Thanks in advance to all,
Regards,
Abhijit
CJ,
The methods / operating procedure will vary from company to company, but here is my take on it.
What is the ideal procedure to have Master P&ID?
There is only ONE master set at any given time. This set is stamped with MASTER and dated.
This is the only P&ID set to be marked up.
When all markups are transferred to CAD, the P&IDs are SUPERSEDED and a new MASTER set is created, stamped, dated and will take the place of the now superseded set.
Ownership of P&IDs is normally by the process department, although piping, instrumentation and electrical departments will have a big influence on them.
After the P&IDs have been Issued For Design, ownership then passes to the piping department, as it is piping who will have the biggest influence on changes to the P&ID.
-How we can make everybody aware & let them know the importance of the P&ID?
Tell them!
-Are we going to use some colour coding like RED for addition, BLUE for deletion & others?
Yes. (Colours may vary from company, but every company should have a standard that must be adhered to.
Example:
Red - Add
Blue - Delete
Green - Comment
Yellow - Checked
-How frequently we should communicate these piping mark ups to process department for approval & implementation on the latest P&IDs?
All changes to the P&IDs by the piping department should be discussed with the process department as thay are being made.
Many companies will insist that ALL changes to the P&ID be signed by piping and counter-singed by process before they can be backdrafted.
-How we can have a real control over this activity?
Usually there will be project guidelines produced at the start of the project to cover this.
-Do we need a special person appointed on the project for this particular activity or there is no need of this?
No, but everyone must be aware of the procedures that the company has set down.
-Most commonly, we will have these kind of mark ups for example-Combining utility lines, PSV outlet lines, addition or deletion of reducers....what are the mark ups other than these are most common? Please give examples?
Any changes that have an effect on the design, should be marked up.
-Can we make a 'SET procedure' for this activity & circulate it amongst the piping team? What can be the procedure?
There SHOULD be a procedure, and the Piping Team, along with the Process Team, the Instrumentation Team and the Electrical Team, should all be familiar with it.
Thank you very much Anton for the very quick & informative answer..!
I will definately make this procedure work succesfully in coming projects..!
Regards,
Abhijit
Thank you very much Anton for the very quick & informative answer..!
I will definately make this procedure work succesfully in coming projects..!
Regards,
Abhijit
Absolutely important point ...I agree completely that All changes to the P&IDs by the piping department should be discussed with the process department as thay are being made...!
Thnx Abhijit
Absolutely important point ...I agree completely that All changes to the P&IDs by the piping department should be discussed with the process department as thay are being made...!
Thnx Abhijit
-Most commonly, we will have these kind of mark ups for example-Combining utility lines, PSV outlet lines, addition or deletion of reducers....what are the mark ups other than these are most common? Please give examples?
Any changes that have an effect on the design, should be marked up.
The process engineer designs drafts P & IDs based on the information he has. While doing piping design, the usage of Tees / Reducing Tees / Reducers depends on the kind of layout / arrangement Piping Designer developes. So sending back the "updated" mark up helps him assess if there's a design impact of it besides synchronizing it with the latest design.
You will notice that mainly the mark-ups that piping have to convey back are for utilities. For example,
1. Utility stations. The number of utility stations depends on the layout and philosophy. For piping designer, it will be pertinent to see that utility stations are provided where necessary and at the same time, the process engineer will worry more about the sizing (heat and mass balance) for these utility stations to work properly.
2. Steam Traps that you add on Steam Headers at pre-decided locations on piperack.
The other typical case is sequence of tappings on the header (distribution P & IDs). It is not just showing the number of tappings but also the correct sequence. This affects the sizing calculation of the header and reducer locations. A simple example would be if the last tapping on a 24" header is 8" and others are of 3". His initial issue indicates the 8" tapping before reducing the header size so the header is reduced to say 6" and you do not update it. Then it will upset his mass balance and then many things down the line.
Timely question:
There is a new Piping Technical Book published recently that includes guidelines for a "Master P&ID Procedure."
This new book, "The Planning Guide To Piping Design" is now listed on the Book List located elsewhere on this piping forum. You can also find this new book by going to amazon.com and typing in the book title in the search window.