October 16, 2007 at 9:00 am
#1492
sabir
Participant
Its like, our client has different class of lines and had given some documents which describes about the CLASS. The Engineering and Design Team has made a Piping Specification out of these documents. So I’m confused whether the Piping Specification is made out of this or is it an independent entity to be designed before the CLASS specification. And now our client want us to verify the Piping Specification as well as we are ought to create the Line list….what are the parameters to be included in the Line List. Hope u understand my question.
Thank you,
Regards
Sabir