    er.piping
    Participant

    Flare headers shall be free draining towards knock out drum
    without any pocket, this was my concept till yesterday..!
    In a new project i am working on a unit flare header is tapped to main header
    unit flare header is at 6 mtr. tier & main header is at 10 mtr. tier. The vertical leg at battery limit
    is having a drip leg kind of arrangement.

    I raised this issue with my boss and he told me that process people has no objection
    to it.
    My question is .. How is it possible..??