  • #7593
    skgarg
    Participant

    Hi Pipers
    Do we need to slope Steam blow Out Pipes ?
    These are the temporary lines used in the start up for the steam blowing cleaning concept for HRSG and main steam lines.
    The problem in sloping these lines is the run of these lines are very long as coming from the Turbine valves and going out of the Building almost 35 meters (due to some noise norms and all) so support concept becomes difficult.
    can I avoid slope in these lines?
    Share your experience!
    Regards
    SG