    zahra
    Participant

    Hi
    I have studied the TDW method as much as they described it in their web site .
    also there will be a committe of profesional engineer which will consider my procedure before execution.
    meanwhile I want to find my flaws.
    what is the diffrence between my idea and what TDW will or other qualified companies do???
    please correct my about weakpoints of my desing.

    PS: In iran all the hot tap operation will be done by national iranian oil company and no forign company can be involved.
    and they have highly qualified team.
    but i am not sure about their method.

    highly appreciated your reply

    #933
    zahra
    Participant

    Hi
    could you please tell me that wheather the split tee is a pressure retaining part or it is just as a reinforcment ??

    I had pland to weld a piece of 20″ pipe on 30″ header and then as a reinforcment fabricate a full or half saddel around header.
    in this way the saddle is not a pressure retaining part and there is no need to have a circomfrencial weld.
    two part of full saddel will be join together with two joining bar.
    then weld a flange to 20″ pipe and and then 20″ full bore ball valve.
    could anybody tell me if this is a practical design or not.