what are input requried to prepare piping specification sheet document?
Please Log in or Create an account to join the conversation.
- Jop
- Offline
- Moderator
Less More
- Posts: 1053
- Thank you received: 14
16 years 3 weeks ago - 16 years 3 weeks ago #4620 by Jop
Do it once and Do it Right
Replied by Jop on topic A list of all commodities
A list of all commodities along with the following for each:
Maximum operating pressure
Maximum operating temperature
Any known short time upset condition
The corrosiveness of the commodity
The planned life of the plant
The corrosion allowance
p.s.: There are times when you really should spell out the words of your question (example: pms vs. Piping Material Specifications).
Maximum operating pressure
Maximum operating temperature
Any known short time upset condition
The corrosiveness of the commodity
The planned life of the plant
The corrosion allowance
p.s.: There are times when you really should spell out the words of your question (example: pms vs. Piping Material Specifications).