When drafting elevation views of riser areas, is it "industry standard" to show the pipe as a hidden linetype when…

3 Posts
1 Users
0 Reactions
70 Views
(@rblogan)
Active Member
Joined: 18 years ago
Posts: 6
Topic starter   [#160]

When drafting elevation views of riser areas, is it "industry standard" to show the pipe as a hidden linetype when it meets grade and continues underground. Please only answer if you know for sure that it's industry standard, as myself and many co-workers I work with are all in disagreement with what is "correct".

Thank you.



   
Quote
(@rblogan)
Active Member
Joined: 18 years ago
Posts: 6
Topic starter  

Crashtested, I appreciate your answer. I also learned the same method of hidden lines in my years of schooling. But, after much arguing and debating with other designers with spans of experience, our company has come to a conclusion.

Any time we're doing a piping plan, we're showing u/g lines as a hidden linetype, which wasn't debated. And drum roll please....any time we're doing a piping elevation (say, at a riser outlet), we're showing u/g lines as a continuous linetype.

My arguement was that if you're showing a section view with grade, or dirt, in between the section and the actual piping, then the piping would be hidden linetype because the dirt is in front of it. But, apparantly when showing a section, we're assuming that the section view takes place right in front of the piping, which means there's no dirt in front of the view. According to many, it has been done like this for years by several different company's which makes it "industry standard". Personally, i don't really care, i just wanted a typical way of doing it.



   
ReplyQuote
(@rblogan)
Active Member
Joined: 18 years ago
Posts: 6
Topic starter  

Crashtested, I appreciate your answer. I also learned the same method of hidden lines in my years of schooling. But, after much arguing and debating with other designers with spans of experience, our company has come to a conclusion.

Any time we're doing a piping plan, we're showing u/g lines as a hidden linetype, which wasn't debated. And drum roll please....any time we're doing a piping elevation (say, at a riser outlet), we're showing u/g lines as a continuous linetype.

My arguement was that if you're showing a section view with grade, or dirt, in between the section and the actual piping, then the piping would be hidden linetype because the dirt is in front of it. But, apparantly when showing a section, we're assuming that the section view takes place right in front of the piping, which means there's no dirt in front of the view. According to many, it has been done like this for years by several different company's which makes it "industry standard". Personally, i don't really care, i just wanted a typical way of doing it.



   
ReplyQuote