Reply
RE: Manual Valve Tags on P&ID's

I've been seeing this requirement also from recent Project I worked with. What I remember though was it is only implemented during detail engineering ...

10 years ago
Forum
Reply
RE: Section - 15E: MTOs, BOMs & BOQs

Thanks Mr. Anton. If you wont mind, could you also provide details on industry norms for the BOQ measurements. I know that it varies from one EPC cont...

10 years ago
Reply
RE: ity Reduced overall cost of the project Cons- Extensive transporatation logistics need to be applied Difficult to…

I would like to move this topic up to share some additional points When modularizing a unit, some decision has to be made whether an equipment shou...

10 years ago
Reply
RE: pipe support from grating floor

Thanks Jop, I agree that this type of support should not be place where grating removal is expected so I guess if ever this type of support is applied...

10 years ago
Topic
Replies: 3
Views: 0
Reply
RE: Piping orthos

In our recent projects, we have proposed to entirely strike out preparation of piping orthos (or piping general arrangement drawings) especially if th...

11 years ago
Reply
RE: Pump Piping

Supports It is recommended to provide adjustable type supports in suction and discharge piping for pump alignment purpose. Y-type strainers I...

11 years ago
Reply
RE: I have few questions... 1

A line requires PWHT and instead of welding a shoe directly at fabshop, a pad was provided instead then heat treated. Is it still required to perfom P...

11 years ago
Reply
RE: Pad on Elbow

Thanks Mr. Jop for the suggestion. However, would that extra section of pipe extended to the supporting point be considered a dead leg?

11 years ago
Topic
11 years ago
Replies: 4
Views: 0
Reply
RE: There is a similar poll running on LinkedIn, so for the wider piping audience, I've copied the poll to here

I think the original topic is not meant to address status of piping design jobs in US alone but on a global perspective. So what if the detail engi...

12 years ago
Reply
RE: Dead End Platform Maximum Length

What would you design that would require a "longer" dead end platform? In some energy company specification, there is also a minimum platform area ...

12 years ago
Reply
RE: Would it be possible to weld a 2" olet onto the back of an 8" equal tee and calling it a special item?

Never tried such arrangement before but have seen several on existing plant built by one respected EPC contractor during the 90s (not sure though if t...

12 years ago